Adjustment steps for extrusion moulds

2025-03-20

 


The general steps for adjustment are as follows:
(1) Check equipments before working

Before starting up, check whether the temperature control is responsive, whether the dashboard in the car is ineffective, and whether the cooling water circuit is smooth. Generally, methods such as using a thermometer and circulating cooling water are used for detection.

(2)Heating up

According to the safety operation regulations of the extruder,heating up the screw extruder, material cylinder, and die head of the extruder. After they reach the set temperature, insulate them for about an hour before starting up to promote long-term temperature maintenance of various parts of the machine equipment.

(3)Check connecting and ensure safty

Before working, make sure tighten the connecting screws and foot screws of each part of the mold head by heat. Before the raw materials are squeezed, workers should not stand directly in front of the die mouth to prevent the foot screws or screws from cracking and causing accidents. When squeezing slowly,slow down the transmission ratio of the screw extruder, and then gradually increase to prevent damage to the parts due to operating load.

(4)Adding raw materials

When starting up, first add a small amount of raw materials and maintain balance feeding. When feeding, pay close attention to various values such as torque. After extruding the raw materials and pulled onto the traction belt mechanical equipment, gradually increase the amount of material until squeezing normally.

(5)Operating the production line carefully

When slowly pulling the belt, keep a certain distance between the shaping mold and the mold head to facilitate the pulling of the belt. Open the waterway (pay attention not to pour water on the die head, otherwise it will disorder feeding of the die head, which will lead to cutting or die plugging), the complex pattern with small inner wall and the aluminum alloy profile with two cavities in the first mock examination need to open the cover plate of the setting die; After confirming the melting of the extruded raw materials is normal, pulling the raw materials onto the optical cable traction machine according to the pre-set traction belt. Reduce the distance between the shaping table and the die head, cover the cover plate, operate the vacuum pump, and wait for the extrusion rate and traction belt speed balanced. Observe the aluminum alloy profile until extruding normally, and then reduce the distance between the shaping table and the die head to a rational value.

(6) Check the producting procedure

If find that the billet does not form at the safety channel end of the forming mold or the inner reinforcement adheres to the inner cavity surface of the aluminum alloy profile, punch several small circular holes at the non formed part or inner reinforcement part of the billet at the channel end of the forming mold using a pointed tool, so that the small inner wall and gas can be fully opened. When the billet enters the forming mold, it is open, which is conducive to creating negative working pressure and pushing the billet to firmly adhere to the mold wall of the forming mold.If the mold is blocked (not blocked), reverse the setting table immediately or increase the traction belt speed, or implemente the two steps together,then adjusted according to the production process to restore normal processing. If the above plan is ineffective due to blockage,reverse the shaping table immediately , and scrape the raw materials along the shaping mold,turned off the water vapor of the shaping mould,reduce the traction belt speed, and pull out the aluminum alloy profile slowly from the shaping mold. If a portion of the aluminum alloy profiles are broken in the shaping mold,disassemble the shaping mold and clean the inventory thoroughly.

(7)Shut down the production line

Shut down the equipment, it is necessary to release the standby material and squeeze out the production and processing materials inside the machine, then wait and use the hot disassembly mold head for cleaning treatment.

Contact us

Anhui Wei Lei Mould Co. Ltd.

If you have any questions to consult, please contact us promptly.
  • Address

    No.1 Yingbin Avenue, West Zone, Economic Development Zone,
    Shijie Town, Guangde City, Xuancheng City, Anhui Province

Send us email

Leave Message